Sealing a concrete joint: sealant type, joint size and backer rod

Updated · Unity Reliance technical team

Most leaking joints are not caused by the sealant itself. They come from the wrong joint shape, poorly prepared joint faces, or sealant stuck to the bottom of the joint. Get those right and almost any good sealant will last.

1. Pick the sealant for the job

Where UNISEAL® product Why
General building joints, precast, parapets, floors UNISEAL® PU One-component polyurethane, no mixing, paintable
Higher-movement building and precast joints UNISEAL® PU PRO Fast-curing PU, Class A, ±25% movement (per TDS)
Water-retaining structures, treatment plants, chemical areas, pavements UNISEAL® PS Two-component polysulphide, chemically curing, non-slumping
Water works, tanks, pools, rainwater systems UNISEAL® MS Polyether One-component MS polymer formulated for water works
Roads, runways, toll plazas, bridge joints UNISEAL® Bituflex Hot-poured rubber bitumen, no primer required
Fire-rated floor and wall joints UNISEAL® VT-629 4-hour fire rating to BS EN 1366-4 (per TDS)

2. Get the joint shape right

  • For joints wider than 12 mm, our details use a sealant width : depth = 2 : 1. A 20 mm wide joint gets about 10 mm of sealant depth. Too deep and the sealant cannot stretch; too shallow and it tears.
  • Tool the surface slightly concave so the sealant is thinnest in the middle.
  • On roads, hot-poured Bituflex is finished slightly below the surface so traffic does not drag it out.

3. Use a backer rod (or filler board) underneath

The backer rod sets the sealant depth and stops the sealant bonding to the joint base:

  • Choose a UNIFLEX® PE backer rod 10–20% wider than the joint, so it stays in compression.
  • Push it in to the correct depth without puncturing it.
  • Over UNIFLEX® PE filler board you do not need a backer rod or bond breaker tape. Over cork (RBCF) or bituminous fibreboard (FB), use bond breaker tape.

4. Prepare, prime, then seal

Clean, dry, sound joint faces, free of laitance, dust and oil. UNISEAL® Primer is required on porous faces (concrete, mortar, masonry), in joints that will be immersed in water and in fire-rated VT-629 joints; on dry, sound, non-porous joints it is optional. Brush it on both faces, let it dry 1 to 2 hours (re-prime if you do not seal within 3 hours), then gun the sealant in and tool it.

5. Avoid three-sided adhesion

If the sealant bonds to the two faces and the bottom of a groove, it cannot stretch and it will split. In sealed grooves over construction joints or induced cracks, put bond breaker tape in the groove base.

Send us the joint width, the movement and where it is (tank, road, building) and we will recommend the UNISEAL® product and backer rod size.

Typical guidance only – not an engineering design. Joint layout, sizes and reinforcement are designed and approved by the project engineer. Refer to each product's TDS.

Do I need bond breaker tape over the filler board?

Not over UNIFLEX® PE or PE FR: closed-cell PE does not bond to the sealant. Over UNIFLEX® RBCF cork or UNIFLEX® FB fibreboard, put bond breaker tape on top of the board before sealing.

What size backer rod do I need?

Choose a UNIFLEX® PE backer rod about 25% larger than the joint width (the UNISEAL® PS data sheet allows 10 to 20%), so it stays in compression. Backer rod comes from 10 mm to 50 mm diameter. Push it in to the correct sealant depth without puncturing it.

What is a bond breaker tape for?

It stops the sealant bonding to the bottom of the joint, so the sealant only sticks to the two joint faces. Without it, a sealant bonded on three sides cannot stretch and splits when the joint opens. It is used in sealant grooves over construction joints and induced cracks, and over cork (RBCF) or fibreboard (FB) filler.

CAD details for this guide

All CAD details

UR-SL-D02UNISEAL®

UNISEAL® Sealant over UNIFLEX® PE Fillerboard

UR-SL-D03UNISEAL®

UNISEAL® Sealed Groove Construction or Control Joint

UR-SL-D04UNISEAL®

UNISEAL® BITUFLEX Sawn Contraction Joint

UR-SL-D06UNISEAL®

UNISEAL® VT-629 Fire Rated Floor Joint

More guides

Request a quotation

Leave your details and we reply by email or WhatsApp, usually within the same working day.